Term Paper on "Cost Benefit Analysis"

Term Paper 5 pages (1407 words) Sources: 4

[EXCERPT] . . . .

benefit Analysis

Cost benefit analysis is a systematic process of comparing and calculating costs and benefits of a project. The benefit of cost-benefit analysis is to determine the justification of a project in order to enhance a sound investment decision. The cost-benefit analysis also assists in comparing projects based on their expected costs and benefits and determines whether the benefits of a project outweigh the costs. Discounting is a technique to compare the present value of a project against the benefits received in different periods in a project lifecycle. (Richard, Zerbe, & Joseph 2010).

Objective of this report is to use a cost-benefit analysis to evaluate the proposed project of National Guard Armory of the State of Massachusetts.

Project Overview

The State of Massachusetts attempts to replace the National Guard armory that is rapidly reaching its service life. According to the Department of Military Affairs, the special maintenance will be $275,000 annually while the rehabilitation of facility would cost $4,000,000, which would extend the armory's service life by 15 years. Based on the information provided, the report calculates the Discount Factor for each year using 4% discount rate for 15 years.

Calculation of Discount Factor of the Project

A discount factor calculates the value that a future sum of money will worth presently. The discount factor of each year of the project is as follows:

Year

Interest Rates

Discount Factor

0

4%


Continue scrolling to

download full paper
/>1

1

4%

0.9615

2

4%

0.9246

3

4%

0.8890

4

4%

0.8548

5

4%

0.8219

6

4%

0.7903

7

4%

0.7599

8

4%

0.7307

9

4%

0.7026

10

4%

0.6756

11

4%

0.6496

12

4%

0.6246

13

4%

0.6006

14

4%

0.5775

15

4%

0.5553

Calculation of the Annual Present Value Cost of Special Maintenance (15 years)

The paper calculates the annual present value costs of special maintenance of the project for 15 years to enhance greater understanding of the overall costs associated to the project. The total costs of special maintenance of the project for 15 years are $4,125,000 and the breakdown is as follows:

Year

Costs of Special Maintenance of Armory ($)

1

275,000

2

275,000

3

275,000

4

275,000

5

275,000

6

275,000

7

275,000

8

275,000

9

275,000

10

275,000

11

275,000

12

275,000

13

275,000

14

275,000

15

275,000

Total Costs of Special Maintenance for 15 years

=275,000x 15,

=$4,125,000

The costs of rehabilitation of the facility costs $4,000,000. Thus, the overall costs of the rehabilitation and maintenance of the project are as follows:

Total Costs to extend the life of the project for 15 years

Total Costs of Special Maintenance for 15 years

$4,125,000

Costs of the Rehabilitation

$4,000,000

Total Costs Invested

$8,125,000

However, the report estimates the potential delays that might occurs before completing the project. Perincherry and Wu (2012) develop a schedule delay cost model and reveal that one year of delay in a new construction project is equivalent of losing an average of 37 cents on every dollar invested in a project. Perincherry and Wu (2012) reveals that the six government constructions are estimated to costs approximately $6.0 Billion in 2011, which is an average of $1 billion per project. Due to the project delay, the estimated costs of the project are $7.5 Billion. The major factors leading to the increase in the costs of a project because of the delay is that there will be an increase in the costs of materials to be used for the project with the effect of inflation. (Richard, Zerbe, & Joseph 2010). Since the National Guard Armory project is a new project, the report will estimate that the Massachusetts will lose 37 cents on every dollar invested in the project in case the project is delayed for one year. Thus, this report assumes that the proposed project will be delayed for one year. The report will integrate the costs of delay in the final report of the costs-benefit analysis.

Calculating Discounted Benefits of Rehabilitating Armory

The report uses the discounting to calculate the benefits that the State Government is going to derive from the project. Discounting is a technique used to translate the costs and benefits of the present-day project values into the time value of money. The time value of money… READ MORE

Quoted Instructions for "Cost Benefit Analysis" Assignment:

National Guard Armory Rehabilitation

1) Use the net present value methodology when creating a cost-benefit analysis to evaluate the following project:

The State of Massachusetts would like to replace a National Guard armory rapidly reaching the end of its service life. The Department of Military Affairs has been told that continued special maintenance would be $275,000 annually. Rehabilitation of facility would cost $4,000,000, and would extend the armory*****s service life by 15 years.

*Calculate the discount factor for each year (use 4% discount rate @ 15 years)

*Calculate the annual present value cost of maintenance (15 years)

*Calculate the discounted benefit of rehabilitating the armory

*Given the discounted cost of rehabilitation, what is the cost- benefit ratio for the proposal?

2) Be sure to include information regarding the following items when completing your evaluation of the project:

*the objectives of the project

*the demand and consumer surplus of the project

*a categorization of the project expenses

*an estimation of potential delays

You should also make sure to:

ï‚· Include an introductory and concluding paragraph

ï‚· Use examples to support your discussion. *****

How to Reference "Cost Benefit Analysis" Term Paper in a Bibliography

Cost Benefit Analysis.” A1-TermPaper.com, 2013, https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455. Accessed 28 Sep 2024.

Cost Benefit Analysis (2013). Retrieved from https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455
A1-TermPaper.com. (2013). Cost Benefit Analysis. [online] Available at: https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455 [Accessed 28 Sep, 2024].
”Cost Benefit Analysis” 2013. A1-TermPaper.com. https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455.
”Cost Benefit Analysis” A1-TermPaper.com, Last modified 2024. https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455.
[1] ”Cost Benefit Analysis”, A1-TermPaper.com, 2013. [Online]. Available: https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455. [Accessed: 28-Sep-2024].
1. Cost Benefit Analysis [Internet]. A1-TermPaper.com. 2013 [cited 28 September 2024]. Available from: https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455
1. Cost Benefit Analysis. A1-TermPaper.com. https://www.a1-termpaper.com/topics/essay/benefit-analysis-cost/7388455. Published 2013. Accessed September 28, 2024.

Related Term Papers:

Role of Cost Benefit Analysis Essay

Paper Icon

Role of Cost Benefit Analysis in Making Security Decisions

Security decisions always reflect cost-benefit analyses, because different jurisdictions and organizations have specific budgets and resources that dictate what programs and… read more

Essay 1 pages (300 words) Sources: 1+ Topic: Environment / Conservation / Ecology


Cost Benefit Analysis and Risk Assessment Essay

Paper Icon

Benefit Analysis and Risk Assessment

The Future of Health Care Costs in Canada

The heath care systems play an increasingly important role within the contemporaneous societies. More money is being… read more

Essay 13 pages (3778 words) Sources: 5 Topic: Healthcare / Health / Obamacare


Healthcare Financing Term Paper

Paper Icon

Childhood Obesity Intervention

Health Promotion Financing

Cost-Benefit Analysis of a Childhood Obesity Intervention

Cost-Benefit Analysis of a Childhood Obesity Intervention

Recent estimates suggest that 16.1% of children between the ages… read more

Term Paper 3 pages (983 words) Sources: 3 Topic: Nutrition / Diet / Eating


Biodiversity in the 2014 British Research Paper

Paper Icon

Builders [were] forced to stop work [for 2 weeks] on the new National Indoor Sports Arena and National Velodrome after asbestos was discovered." Local residents loudly complained to the news… read more

Research Paper 10 pages (3015 words) Sources: 10 Style: Harvard Topic: Environment / Conservation / Ecology


Red Light Cameras Cost Benefit Analysis Term Paper

Paper Icon

Red Light Cameras

Cost Benefit Analysis of Red Light Cameras

The United States Department of Transportation published a study in 2005 which compared the costs of crashes in intersections with… read more

Term Paper 2 pages (637 words) Sources: 1 Style: APA Topic: Transportation / Mass Transit


Sat, Sep 28, 2024

If you don't see the paper you need, we will write it for you!

Established in 1995
900,000 Orders Finished
100% Guaranteed Work
300 Words Per Page
Simple Ordering
100% Private & Secure

We can write a new, 100% unique paper!

Search Papers

Navigation

Do NOT follow this link or you will be banned from the site!